Phase 5
 

 

Technical details of the expansion

  • 9 new tanks with a total capacity of 380,000 cbm
  • capacity of tanks ranging from 20,000 to 60,000 cbm
  • 1 new berth for vessels up to 110,000 dwt
  • 1 new berth for vessels up to 60,000 dwt
  • 3 loading arms, 16’, for white products
  • 3 loading arms, 16’, for black products

 

 

 May 2008

Pile driving for the new berths

   

SHE promotion award 
Phase-V, Offshore

For the month of April 2008

1. Gopalan  Monikantan  ( TME- NICO  International  )
2. Mohammad  Iqbal  ( TME  )
3. Phazur Karunan Pancker  (  TME- DULSCO ) 
4.  Mohammad  Zaid  ( TME )

   

SHE promotion award 
Phase-V, Offshore

For the month of March 2008

1. Shankar  ( TME-NICO )
2.  B. Corcurrea  ( TME-B.I.T   Logistic  )
3. Padam  Bahadur  (  TME- DULSCO )
4.  Haroun  Abdul  Raman  -(  TME- B.I.T Logistics )
5.  Zubir  Chirammel  (  TME )

   

SHE promotion award 
Phase-V, Offshore

For the month of February 2008

1. Bineesh  ( TME- DULSCO )
2.  Endwin  Sim    (  TME)
3.  Jegath  Kumarasiri  ( TME- NICO)
4. Azmi  Bin Che Daud  ( TME )
5.  Look  Cheefai  --       (  TME )

 

SHE promotion award 
Phase-V, Offshore

For the month of January 2008

1. Naval  Singh  ( TME- NICO )
2.  Ayub  bin abdul  wahab   (  TME )
3.  Jalal   Ahamad  ( TME- DULSCO )

   November 2007

Lifting of dome roof of TK 509. With the TK 509 roof installation the last major building activity is completed.

   

 November 2007

Arrival of the piles for the new jetties. In total 438 pieces were transported from the Port of Fujairah to site by trucks at a 24 hours per day operation. The pile lengths are 219 x 24 m and 219 x 14 m with a total weight of approximately 3500 tons.

 

 

  November 2007
The on shore part of phase V will be ready for commissioning by 31 December 2007
 
Safety Award 2007

Safety Promotion awards for the month of  September-07 were distributed to the following workers.

P. Subburaj (Cylingas)
Ananda Rao (Cylingas)
Basfraj Malakanna (Emirates Technical Services)
Meke Thapa Chettri (C.A.T.)
K. Radhakrishnan (Group 4)

The above personnel when deputed to critical activities found working in the safest manner. They are well aware of safety procedures, and their cooperation with co workers is excellent and pleasing.
They were observed by Safety Officers, supervisors and found using proper PPE all the time, attentive on tool box talk and explaining to others in the team.

 

September 2007
During the Vopak Oil EMEA Safety Day, September 6th 2007, the Phase V Safety Awards of July and August were distributed to:

K. Moideen Kutty - Consilium
Jit Bahadur - Consilium
B. Srinivas Rao - Cylingas
G. Linga Raju - Cylingas
Younus Khan - Cylingas
V.S. Vishnu - Cylingas
Dasandla Devanandam - Cylingas
Sanawar Khan - CAT
Genesh Chamar - CAT
Talaat - CAT

In August 441 contractors worked at the terminal and a milestone of 1,000,000 man hours was reached!

 

 

August 2007
Construction is on schedule, out of the total nine tanks three tanks are painted and eight dome roofs are positioned. The last tank reached 50% of its height. Meantime piping, civil and Electronic/Informationsystems works continue.

 

Safety Award June 2007
The safety promotion awards for the month of June 2007 were distributed to;

Madhava Rao - Cylingas
Ashfar Ahmed Muhammad Aslam - Cylingas
Sakail Venkat Narsayya - CAT
Ramesh - Group4

Well done and congratulations!

  June 2007 
Hydro test of the first 4 tanks is carried out.
 

Safety award May 2007

This month's safety award is won by:
Midare Shinakestama --  contractor C.A.T.
D. Appala Swamy --  contractor Cylingas
M. Kamayya --  contractor Cylingas

Well done and congratulations!

 

   

Safety award April 2007
Besides distributing the Safety Promotion Awards for the month of April, 500,000 manhours without LTA/LTI was celebrated.
All contractors received a very nice VHFL-shirt and a refreshment. Well done!


 

 

May 2007
Raising domes on tanks 505 and 507

 

Safety award March 2007
Safety Promotion awards for the month of March were distributed to 4 workers of the contractors based on the following criteria.

· Safety awareness & alertness
· Aware of safety procedures.
· Aware of emergency response at the time of fire & medical emergencies
· No safety violations
· Always found using appropriate PPE
· Active participation in house keeping & Tool box training meeting

Yohannan Valandry Thambi **  (C.A.T.)
Pattayya                                (Cylingas)
Nageswara Rao                      (Cylingas)
Vapputy                                 (Group 4 Security Services)

  April 2007
Concrete reinforcement is being laid out for the Pumppit
  April 2007
At this moment 4 tanks have reached its max. height of 25 m and 4 other tanks are 5 - 10 m high.
The roof erection of the first tank will start this month.
 

Safety award February 2007

Granting this month's Safety Award to the contractor employees who performed best with regarding to safety.

- Y. Chenna Rao (Cylingas)
- P. Rama Murthy (Cylingas)
- Wakil Khan (C.A.T.)
- Frederick Gimenez (C.A.T)
received this month's award because:
· Safe working habits with minimum supervision.
· Aware of safety procedures.
· Aware of emergency response at the time of fire & medical emergencies
· No safety violations
· Always found using appropriate PPE
· Active participation in house keeping & Tool box training meeting

 

 February 2007

Seven shell courses of 2.5 metres each have been erected for four tanks, two shell courses for two tanks and one shell course for another two tanks.


 

 

Safety award January 2007


J. Madhavayya, K. Hema Rao,
G. Buenaventura, Prasad P.V.

received January's safety award because of :

  • Safe Working habits and very co-operative when it comes to safety.
  • No safety violation since the beginning of the project
  • Always found using appropriate PPE
  • Active participation in house keeping & Tool box training meeting
  • No complaints from security, colleagues and peers.
  • Reporting Hazards and Near Misses

Well done and congratulations!
    

  January 2007
The new tanks have already a height of 7,5 metres. The total height will become 25 metres.

In front of these tanks you can see the tank bottoms of another few new to build tanks.

February 1st,  the improvement of tank bottom 509 will start.

 

  December 2006
Granting this month's Safety Award to the contractor employees who performed best with regarding to safety.

Nasser Anser, Aji Manoharan, Bijay Biswas
received this month's award because:
  • They are hardworking and very cooperative when it comes to Safety and they have made no safety violation since the beginning of the project.
  • These workers were found wearing the basic Personal Protective Equipment always at site and attend weekly tool box regularly.
  • Active participation in housekeeping
  • and there are no complaints from security personnel, their colleagues or their peers against them

Well done and congratulations!

  November 2006
Granting this month's Safety Award to the contractor employees who performed best with regarding to safety.

Abdul Basheer Kariveetill, Satan Singh, Kanaka Raj received this month's award because:

  • They are hardworking and very cooperative when it comes to Safety and they have made no safety violation since the beginning of the project.
  • These workers were found wearing the basic Personal Protective Equipment always at site and attend weekly tool box regularly.
  • Active participation in housekeeping
  • and there are no complaints from security personnel, their colleagues or their peers against them

Well done and congratulations!


  November 2006
Puja cermony 

The Puja ceremony is a Hindu ceremony performed on special occasions. At this picture our Terminal Manager is cracking a coconut, which is part of the Puja ceremony.
 

November 2006
The first bottom plate.

 

 

 

October 2006
Granting this month's Safety Award to the contractor employees who performed best with regarding to safety.

Arjun Khand, Khale Sherpa en Bensi Behadur received this month's award because:

  • They are hardworking and very cooperative when it comes to Safety and they have made no safety violation since the beginning of the project.
  • These workers were found wearing the basic Personal Protective Equipment always at site and attend weekly tool box regularly.
  • Active participation in housekeeping
  • and there are no complaints from security personnel, their colleagues or their peers against them

Well done and congratulations!

  October 2006
Construction of tank bottoms.
  September 2006
Granting this month's Safety Award to the contractor employee who performed best with regarding to safety.
  September 2006
Preparing tank foundation
   

August 2006
Three vibro compaction rigs

Construction work of Phase V at Fujairah has started. Soil improvement by vibro compaction has to be done. Vibro compaction is done by installing sand/rock columns, in total 5,600 columns have to be made.


 

 
Slogan